Penwortham 400kV Substation

Penwortham 400kV Substation (NGET) has 7 projects in NESO's TEC Register of 23 Oct 2026: 2,694 MW in the queue, 57 MW of it Gate 2, 657 MW Gate 1, and 60 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
7
MW in the queue
2,694 MW
Gate 2 MW
57 MW
Gate 1 MW
657 MW
MW connected
60 MW
Earliest confirmed date
30 Oct 2028

By technology

TechnologyProjectsMW
Offshore wind21,980
Storage4754
Demand1600
Solar1600
Gas120

Projects at Penwortham 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Morgan Offshore Wind FarmOffshore wind1,500Scoping30 Nov 2029
Penwortham Green Energy CentreDemand, Storage, Solar600Gate 1Awaiting Consents30 Oct 2035
Morecambe Offshore Wind FarmOffshore wind480Scoping30 Jun 2029
Penwortham BESSStorage57Gate 1Scoping1 Jun 2031
Penwortham BESSStorage57Gate 2Consents Approved30 Oct 2028
Penwortham (Redscar)Storage40Built
Bispham BEGAGas20Built