Pentir 400kV Substation

Pentir 400kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 1,082 MW in the queue, 57 MW of it Gate 2, 1,025 MW Gate 1, and 39 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
1,082 MW
Gate 2 MW
57 MW
Gate 1 MW
1,025 MW
MW connected
39 MW
Earliest confirmed date
31 Oct 2028

By technology

TechnologyProjectsMW
Storage21,082
Demand11,025
Solar11,025
Hydro139

Projects at Pentir 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Pentir Green Energy CentreDemand, Storage, Solar1,025Gate 1Awaiting Consents30 Oct 2037
Fferm Solar PentirStorage57Gate 2Consents Approved31 Oct 2028
DolgarrogHydro39Built