Penninghame Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 60 MW in the queue, 60 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
60 MW
Gate 1 MW
60 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind160

Projects at Penninghame Substation

ProjectTechnologyMWGateStatusMW effective from
Penninghame Wind FarmOnshore wind60Gate 1Scoping31 Oct 2031