Pembroke 400kV Substation

Pembroke 400kV Substation (NGET) has 9 projects in NESO's TEC Register of 23 Oct 2026: 1,705 MW in the queue, 350 MW of it Gate 2, 540 MW Gate 1, and 2,199 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
9
MW in the queue
1,705 MW
Gate 2 MW
350 MW
Gate 1 MW
540 MW
MW connected
2,199 MW
Earliest confirmed date
7 Mar 2029

By technology

TechnologyProjectsMW
Demand12,199
Hydrogen12,199
Offshore wind4895.25
Storage4809.9
Solar199.9

Projects at Pembroke 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Pembroke Power StationDemand, Hydrogen2,199Built
Pembroke BESSStorage285–350Gate 2Consents Approved7 Mar 2029, 25 May 2029
Llywelyn Floating Offshore Wind FarmOffshore wind300Gate 1Scoping31 Mar 2029
Valorous Offshore Wind FarmOffshore wind300Scoping31 Oct 2031
Lambeeth 240MWStorage240Gate 1Scoping31 Dec 2037
Llŷr Floating WindOffshore wind200Scoping31 Oct 2028
Pembroke (spare bay)Storage120Consents Approved30 Jul 2028
Pembroke BESS and Solar StationStorage, Solar99.9Awaiting Consents31 Oct 2028
ErebusOffshore wind95.25Scoping26 Jul 2028

Source