Peat Law Renewable Energy Park 132kV Substation

Peat Law Renewable Energy Park 132kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 253.28 MW in the queue, 253.28 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
253.28 MW
Gate 1 MW
253.28 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1253.28
Solar1253.28
Storage1253.28

Projects at Peat Law Renewable Energy Park 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Peat Law Renewable Energy ParkStorage, Solar, Onshore wind253.28Gate 1Scoping30 May 2033