Norwich Main 400kV Substation

Norwich Main 400kV Substation (NGET) has 6 projects in NESO's TEC Register of 23 Oct 2026: 4,535 MW in the queue, 28 MW Gate 1, and 420 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
6
MW in the queue
4,535 MW
Gate 1 MW
28 MW
MW connected
420 MW

By technology

TechnologyProjectsMW
Offshore wind24,350
Storage33,157
Gas1420
Solar285
Onshore wind128

Projects at Norwich Main 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Hornsea Power Station 3Storage, Offshore wind2,250–3,000Consents Approved1 Oct 2026, 31 Dec 2028
Scira-Dudgeon ExtensionOffshore wind719–1,350Scoping1 Jan 2030, 31 Oct 2031, 1 Oct 2034
Great YarmouthGas420Built
Norwich 100MW BESSStorage99.9Scoping31 Oct 2031
NorwichStorage, Solar57Consents Approved18 Dec 2025
Norwich 2Solar, Onshore wind28Gate 1Scoping30 Jun 2033