Norton East 400kV Substation

Norton East 400kV Substation (NGET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 1,630 MW in the queue, 1,390 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
5
MW in the queue
1,630 MW
Gate 1 MW
1,390 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage51,630
Solar41,480
Demand1600

Projects at Norton East 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Letch Beck Energy ParkDemand, Storage, Solar600Gate 1Scoping31 Oct 2033
NortonStorage, Solar400Gate 1Scoping31 Oct 2032
Grindon GrangeStorage, Solar240Scoping30 Oct 2035
Lightsource Norton East PVStorage, Solar240Gate 1Scoping30 Oct 2035
Zenobe NortonStorage150Gate 1Awaiting Consents31 Oct 2031