Grid GuardianOpen this site in the app

North Humber Connection Node C 132kV Substation

North Humber Connection Node C 132kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 240 MW in the queue, 200 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
240 MW
Gate 1 MW
200 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage2240

Projects at North Humber Connection Node C 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Thornton BESSStorage200Gate 1Scoping30 Oct 2035
014 NEP BransholmeStorage40Scoping30 Oct 2035

Source