North Anglia Connection Node A 400kV
North Anglia Connection Node A 400kV (NGET) has 11 projects in NESO's TEC Register of 23 Oct 2026: 4,623 MW in the queue, 4,518 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 11
- MW in the queue
- 4,623 MW
- Gate 1 MW
- 4,518 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 11 | 4,623 |
| Solar | 5 | 3,010 |
Projects at North Anglia Connection Node A 400kV
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Norwich Main BESS | Storage, Solar | 249.9–949.9 | Gate 1 | Scoping | 31 Oct 2032, 31 Oct 2034 |
| Elmya Gissing BESS & PV | Storage, Solar | 900 | Gate 1 | Scoping | 31 Oct 2034 |
| Noventum -Long Stratton | Storage, Solar | 460 | Gate 1 | Scoping | 30 Oct 2038 |
| GF Norwich BESS | Storage | 400 | Gate 1 | Scoping | 31 Oct 2032 |
| Long Stratton 400 | Storage, Solar | 400 | Gate 1 | Scoping | 31 Oct 2034 |
| Long Stratton BESS | Storage | 400 | Gate 1 | Scoping | 31 Oct 2034 |
| Swainsthorpe | Storage, Solar | 300 | Gate 1 | Scoping | 31 Oct 2037 |
| Intwood Farm BESS | Storage | 240 | Gate 1 | Scoping | 31 Oct 2034 |
| Wacton Road Farm | Storage | 240 | Gate 1 | Scoping | 30 Oct 2034 |
| Wymondham Road Farm | Storage | 228 | Gate 1 | Scoping | 31 Oct 2034 |
| Old Stoke Rd BESS | Storage | 105 | Scoping | 31 Oct 2034 |
Source