Grid GuardianOpen this site in the app

Newchurch 400kV Substation

Newchurch 400kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 400 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
400 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Demand1400
Solar1400
Storage1400

Projects at Newchurch 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
NewchurchDemand, Storage, Solar400Scoping4 Oct 2031