New Dounreay 400kV substation

New Dounreay 400kV substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 1,700 MW in the queue, 1,700 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
2
MW in the queue
1,700 MW
Gate 1 MW
1,700 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Offshore wind11,500
Storage1200

Projects at New Dounreay 400kV substation

ProjectTechnologyMWGateStatusMW effective from
HavbredeyOffshore wind1,500Gate 1Scoping30 Oct 2033
Dounreay BESSStorage200Gate 1Scoping31 Oct 2034