New Connagill 275/132kV Substation
New Connagill 275/132kV Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 220 MW in the queue, 220 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 220 MW
- Gate 1 MW
- 220 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 2 | 220 |
Projects at New Connagill 275/132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Gresham House Connagill BESS | Storage | 170 | Gate 1 | Scoping | 31 Oct 2031 |
| 50MW BESS Connagill | Storage | 50 | Gate 1 | Scoping | 31 Oct 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.