Grid GuardianOpen this site in the app

New Abernethy 132kV

New Abernethy 132kV (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 50 MW in the queue, 50 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
50 MW
Gate 1 MW
50 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage150

Projects at New Abernethy 132kV

ProjectTechnologyMWGateStatusMW effective from
Jamesfield 3Storage50Gate 1Scoping31 Oct 2037