Mybster 2 132/33kV Substation

Mybster 2 132/33kV Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 85.9 MW in the queue, 36 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
2
MW in the queue
85.9 MW
Gate 1 MW
36 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage149.9
Onshore wind136

Projects at Mybster 2 132/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
SPITTALStorage49.9Scoping30 Oct 2030
Cogle Moss Wind FarmOnshore wind36Gate 1Scoping31 Aug 2025