Mossmorran Storage BESS 132KV Substation
Mossmorran Storage BESS 132KV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 100 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 1
- MW in the queue
- 100 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 1 | 100 |
Projects at Mossmorran Storage BESS 132KV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Mossmorran Storage BESS | Storage | 100 | Scoping | 31 Oct 2031 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.