Monk Fryston 275kV Substation
Monk Fryston 275kV Substation (NGET) has 8 projects in NESO's TEC Register of 23 Oct 2026: 2,670 MW in the queue, 849.9 MW Gate 1, and 57 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 8
- MW in the queue
- 2,670 MW
- Gate 1 MW
- 849.9 MW
- MW connected
- 57 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 8 | 2,727 |
| Solar | 3 | 1,700 |
Projects at Monk Fryston 275kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Monk Fryston Energy Park | Storage, Solar | 800 | Scoping | 24 Oct 2035 | |
| Monk Fryston | Storage, Solar | 500 | Scoping | 31 Dec 2029 | |
| Monk Fryston | Storage, Solar | 400 | Gate 1 | Scoping | 31 Oct 2031 |
| Monk Fryston SSE | Storage | 320 | Consents Approved | 31 Oct 2025 | |
| Monk Fryston | Storage | 249.9 | Gate 1 | Scoping | 30 Oct 2035 |
| Kingfisher Farm | Storage | 200 | Gate 1 | Scoping | 2 Jun 2036 |
| Monk Fryston BESS | Storage | 200 | Scoping | 31 Oct 2029 | |
| Monk Fryston Tertiary Connection | Storage | 57 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.