Minety 400kV Substation

Minety 400kV Substation (NGET) has 10 projects in NESO's TEC Register of 23 Oct 2026: 427.5 MW in the queue, and 19 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
10
MW in the queue
427.5 MW
MW connected
19 MW

By technology

TechnologyProjectsMW
Storage10446.5
Solar3142.5

Projects at Minety 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Dog Trap LaneStorage47.5Consents Approved31 Oct 2028
Fairholme BESSStorage47.5Consents Approved28 Feb 2025
JBM Solar -MinetyStorage, Solar47.5Scoping30 Nov 2028
MinetyStorage47.5Consents Approved31 Oct 2024
Pond Hill Farm 1Storage47.5Consents Approved30 Apr 2025
Pond Hill Farm 2 BESSStorage47.5Consents Approved31 May 2025
SomerfordStorage, Solar47.5Consents Approved30 Jun 2025
SouthfieldsStorage, Solar47.5Awaiting Consents30 Jun 2025
Southfields FarmStorage47.5Consents Approved31 Oct 2028
Conrad (Swindon) LimitedStorage19Built