Milton of Craigie GSP

Milton of Craigie GSP (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 67.9 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
2
MW in the queue
67.9 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage267.9
Solar118

Projects at Milton of Craigie GSP

ProjectTechnologyMWGateStatusMW effective from
Pitkerro RoadStorage49.9Scoping31 Oct 2033
Barns of Wedderburn (ABEI ENERGY GREEN VI)Storage, Solar18Scoping31 Oct 2033