Grid GuardianOpen this site in the app

Melvich Community Wind Farm 132/33kV Substation

Melvich Community Wind Farm 132/33kV Substation (SHET) has 1 project in NESO's TEC Register of 23 Oct 2026: 57.6 MW in the queue, 57.6 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
1
MW in the queue
57.6 MW
Gate 1 MW
57.6 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind157.6
Storage157.6

Projects at Melvich Community Wind Farm 132/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Melvich Wind Energy HubStorage, Onshore wind57.6Gate 1Awaiting Consents1 Apr 2030

Source