Grid GuardianOpen this site in the app

Manchester South connection node A 400kv

Manchester South connection node A 400kv (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 740 MW in the queue, 740 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
740 MW
Gate 1 MW
740 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage2740

Projects at Manchester South connection node A 400kv

ProjectTechnologyMWGateStatusMW effective from
Daines NP BESSStorage500Gate 1Scoping30 Oct 2037
Siddington BESS StationStorage240Gate 1Scoping30 Oct 2037