Grid GuardianOpen this site in the app

Littlebrook 132kV Substation

Littlebrook 132kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 607 MW in the queue, 57 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
607 MW
Gate 1 MW
57 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage3607
Solar157

Projects at Littlebrook 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Littlebrook BESSStorage300Scoping15 Oct 2027
Low Carbon Energy Centre BESS Joyce Green LaneStorage250Scoping31 Oct 2037
ER LBR EnergyStorage, Solar57Gate 1Scoping17 Oct 2029

Source