Linnmill 132/33kV

Linnmill 132/33kV (SPT) has 3 projects in NESO's TEC Register of 23 Oct 2026: 20 MW in the queue, and 71 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
3
MW in the queue
20 MW
MW connected
71 MW

By technology

TechnologyProjectsMW
Onshore wind391
Storage120

Projects at Linnmill 132/33kV

ProjectTechnologyMWGateStatusMW effective from
Auchrobert Wind FarmOnshore wind36Built
Andershaw Wind FarmOnshore wind35Built
Brae WFStorage, Onshore wind20Scoping30 Aug 2032

Source