Leeds North Connection Node C 400kV Substation

Leeds North Connection Node C 400kV Substation (NGET) has 8 projects in NESO's TEC Register of 23 Oct 2026: 2,970 MW in the queue, 2,290 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
8
MW in the queue
2,970 MW
Gate 1 MW
2,290 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage82,970
Solar21,200
Nuclear11,000
Onshore wind11,000

Projects at Leeds North Connection Node C 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Brodsworth High Impact Green Energy Hub (Brodsworth HIGEH)Storage, Nuclear, Solar, Onshore wind1,000Gate 1Scoping30 Oct 2035
FCC Thurcroft BESSStorage750Gate 1Scoping31 Oct 2033
NEL BluebellStorage240Scoping30 Oct 2035
NEL Conway2Storage240Gate 1Scoping31 Oct 2035
NEL SpringfieldStorage240Scoping30 Oct 2035
Ferrybridge B - NEL HunterStorage200Scoping30 Oct 2035
West Melton PV & BESS StationStorage, Solar200Gate 1Scoping30 Oct 2035
Fryston Lane 100MW BESSStorage100Gate 1Scoping31 Oct 2035