Langage 400kV Substation

Langage 400kV Substation (NGET) has 4 projects in NESO's TEC Register of 23 Oct 2026: 1,649 MW in the queue, 1,400 MW Gate 1, and 905 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
4
MW in the queue
1,649 MW
Gate 1 MW
1,400 MW
MW connected
905 MW

By technology

TechnologyProjectsMW
Storage31,649
Solar21,400
Gas1905

Projects at Langage 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Langage FarmStorage, Solar1,000Gate 1Scoping19 Dec 2037
LangageGas905Built
Langage 400Storage, Solar200–400Gate 1Scoping19 Dec 2036, 31 Oct 2037, 31 Oct 2038
Langage Battery StorageStorage249Scoping30 Oct 2031