Lackenby 400kV Substation
Lackenby 400kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 1,800 MW in the queue, 600 MW Gate 1, and 1,320 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 3
- MW in the queue
- 1,800 MW
- Gate 1 MW
- 600 MW
- MW connected
- 1,320 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Offshore wind | 2 | 2,520 |
| Solar | 1 | 600 |
| Storage | 1 | 600 |
Projects at Lackenby 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Sofia Offshore Wind Farm | Offshore wind | 1,320 | Built | ||
| Dogger Bank Project C | Offshore wind | 1,200 | Consents Approved | 1 Apr 2025 | |
| Crathorne Estate BESS and Solar Farm | Storage, Solar | 600 | Gate 1 | Scoping | 30 Oct 2035 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.