Kirkby 275/33kV Substation

Kirkby 275/33kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 514 MW in the queue, 57 MW of it Gate 2, 457 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
514 MW
Gate 2 MW
57 MW
Gate 1 MW
457 MW
MW connected
0 MW
Earliest confirmed date
31 Oct 2027

By technology

TechnologyProjectsMW
Storage3514
Solar2457
Demand1400

Projects at Kirkby 275/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Kirkby Green Energy CentreDemand, Storage, Solar400Gate 1Scoping30 Oct 2028
KirkbyStorage49.9–57Gate 2Consents Approved31 Oct 2027, 30 Oct 2037
Kirkby (Tertiary)Storage, Solar57Gate 1Scoping30 Aug 2027