Kilmarnock Town 275/33kV Substation

Kilmarnock Town 275/33kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 60 MW in the queue, 60 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
60 MW
Gate 2 MW
60 MW
MW connected
0 MW
Earliest confirmed date
8 Feb 2027

By technology

TechnologyProjectsMW
Storage160

Projects at Kilmarnock Town 275/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Inchbean Energy ParkStorage60Gate 2Consents Approved8 Feb 2027