Grid GuardianOpen this site in the app

Killoch BESS 132kV Substation

Killoch BESS 132kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 150 MW in the queue, 150 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
150 MW
Gate 1 MW
150 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage1150

Projects at Killoch BESS 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
Killoch BESSStorage150Gate 1Scoping30 Sept 2030

Source