Killingholme 400kV Substation
Killingholme 400kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 1,040 MW in the queue, and 619 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 3
- MW in the queue
- 1,040 MW
- MW connected
- 619 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Gas | 2 | 1,159 |
| Solar | 1 | 500 |
| Storage | 1 | 500 |
Projects at Killingholme 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Killingholme | Gas | 619 | Built | ||
| North Killingholme Power Project | Gas | 540 | Consents Approved | 30 Sept 2030 | |
| THE CLEAN FUTURE | Storage, Solar | 500 | Scoping | 31 May 2033 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.