Kilbraur Wind Farm Substation
Kilbraur Wind Farm Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 79.2 MW in the queue, 79.2 MW Gate 1, and 67 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 79.2 MW
- Gate 1 MW
- 79.2 MW
- MW connected
- 67 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 2 | 146.2 |
Projects at Kilbraur Wind Farm Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Kilbraur North Wind Farm | Onshore wind | 79.2 | Gate 1 | Scoping | 31 Oct 2031 |
| Kilbraur Wind Farm | Onshore wind | 67 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.