Ironbridge 400kV Substation

Ironbridge 400kV Substation (NGET) has 3 projects in NESO's TEC Register of 23 Oct 2026: 1,300 MW in the queue, 700 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
3
MW in the queue
1,300 MW
Gate 1 MW
700 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage31,300
Solar21,000

Projects at Ironbridge 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
IronbridgeStorage, Solar600Scoping30 Apr 2031
Ironbridge Green Energy CentreStorage, Solar400Gate 1Awaiting Consents30 Oct 2029
ELMYA REDNALStorage300Gate 1Awaiting Consents30 Oct 2034