Hunningley 132kV Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 40 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 1
- MW in the queue
- 0 MW
- MW connected
- 40 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 1 | 40 |
Projects at Hunningley 132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Hunningley Stairfoot BESS | Storage | 40 | Built |