Humber Gateway 33/132kV Offshore Substation

Humber Gateway 33/132kV Offshore Substation (OFTO) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 220 MW connected. Contracted capacity, not headroom.

Transmission owner
OFTO
Projects
1
MW in the queue
0 MW
MW connected
220 MW

By technology

TechnologyProjectsMW
Offshore wind1220

Projects at Humber Gateway 33/132kV Offshore Substation

ProjectTechnologyMWGateStatusMW effective from
Humber Gateway Offshore Wind FarmOffshore wind220Built