Hornsea Platform 1B Offshore Substation
Hornsea Platform 1B Offshore Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 0 MW in the queue, and 400 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 1
- MW in the queue
- 0 MW
- MW connected
- 400 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Offshore wind | 1 | 400 |
Projects at Hornsea Platform 1B Offshore Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Hornsea Power Station 1B | Offshore wind | 400 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.