Helensburgh 132/33kV
Helensburgh 132/33kV (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 39.9 MW in the queue, 39.9 MW of it Gate 2, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 1
- MW in the queue
- 39.9 MW
- Gate 2 MW
- 39.9 MW
- MW connected
- 0 MW
- Earliest confirmed date
- 29 Oct 2027
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 1 | 39.9 |
Projects at Helensburgh 132/33kV
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Drumfad Battery Storage System | Storage | 39.9 | Gate 2 | Consents Approved | 29 Oct 2027 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.