Hawick 132kV Substation
Hawick 132kV Substation (SPT) has 4 projects in NESO's TEC Register of 23 Oct 2026: 406.8 MW in the queue, 264 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 4
- MW in the queue
- 406.8 MW
- Gate 1 MW
- 264 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 4 | 406.8 |
| Storage | 1 | 150 |
Projects at Hawick 132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Woodland Ridge | Storage, Onshore wind | 150 | Gate 1 | Scoping | 3 Jul 2034 |
| Brown Rig Wind Farm | Onshore wind | 114 | Gate 1 | Scoping | 31 Oct 2033 |
| Millmoor Rig Wind Farm | Onshore wind | 92.8 | Scoping | 30 Oct 2029 | |
| Pines Burn Wind Farm | Onshore wind | 50 | Consents Approved | 2 Aug 2023 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.