Grid GuardianOpen this site in the app

Hare Hill Repowering 132/33kV Substation

Hare Hill Repowering 132/33kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 114 MW in the queue, 114 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
114 MW
Gate 1 MW
114 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1114

Projects at Hare Hill Repowering 132/33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Hare Hill RepoweringOnshore wind114Gate 1Scoping31 Oct 2031