Hare Craig 33kV Substation

Hare Craig 33kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 46.2 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
46.2 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind146.2

Projects at Hare Craig 33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Hare Craig Wind FarmOnshore wind46.2Awaiting Consents31 Oct 2028