Hams Hall 400kV Substation

Hams Hall 400kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 1,425 MW in the queue, 399.9 MW of it Gate 2, 1,025 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
1,425 MW
Gate 2 MW
399.9 MW
Gate 1 MW
1,025 MW
MW connected
0 MW
Earliest confirmed date
30 Oct 2026

By technology

TechnologyProjectsMW
Storage21,425
Demand11,025
Solar11,025

Projects at Hams Hall 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
Hams Hall Green Energy CentreDemand, Storage, Solar400–1,025Gate 1Scoping30 Oct 2028, 31 Oct 2032
WELBAR ENERGY STORAGEStorage349.9–399.9Gate 2Consents Approved30 Oct 2026, 31 Oct 2032