Grid GuardianOpen this site in the app

Greystones A 275kV Substation

Greystones A 275kV Substation (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 700 MW in the queue, and 150 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
700 MW
MW connected
150 MW

By technology

TechnologyProjectsMW
Gas1700
Storage1150

Projects at Greystones A 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
Wilton CCGT Project 2Gas700Consents Approved30 Oct 2035
Wilton Lion BESSStorage150Built

Source