Glentaggart WF 33kV Substation

Glentaggart WF 33kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 42 MW in the queue, 42 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
42 MW
Gate 1 MW
42 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage142

Projects at Glentaggart WF 33kV Substation

ProjectTechnologyMWGateStatusMW effective from
Glentaggart 42MW BESSStorage42Gate 1Scoping31 Oct 2027