Glen Ullinish 132/33kV Substation
Glen Ullinish 132/33kV Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 289.9 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 289.9 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Onshore wind | 2 | 289.9 |
Projects at Glen Ullinish 132/33kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Glen Ullinish Extension | Onshore wind | 240 | Awaiting Consents | 31 Aug 2029 | |
| Glen Ullinish Wind Farm | Onshore wind | 49.9 | Consents Approved | 16 Apr 2028 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.