GH DEVCO KINCARDINE BESS 132kV SUBSTATION

GH DEVCO KINCARDINE BESS 132kV SUBSTATION (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 42 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
42 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage142

Projects at GH DEVCO KINCARDINE BESS 132kV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
GH DEVCO Kincardine BESSStorage42Scoping31 Oct 2029