GH DEVCO KINCARDINE BESS 132kV SUBSTATION
GH DEVCO KINCARDINE BESS 132kV SUBSTATION (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 42 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 1
- MW in the queue
- 42 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 1 | 42 |
Projects at GH DEVCO KINCARDINE BESS 132kV SUBSTATION
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| GH DEVCO Kincardine BESS | Storage | 42 | Scoping | 31 Oct 2029 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.