Galileo 16 132kV Substation

Galileo 16 132kV Substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 125 MW in the queue, 125 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
125 MW
Gate 1 MW
125 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind1125
Solar1125
Storage1125

Projects at Galileo 16 132kV Substation

ProjectTechnologyMWGateStatusMW effective from
GALILEO 16Storage, Solar, Onshore wind125Gate 1Scoping29 Oct 2032

Source