Fyrish 132kV Substation
Fyrish 132kV Substation (SHET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 370 MW in the queue, 370 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 2
- MW in the queue
- 370 MW
- Gate 1 MW
- 370 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 2 | 370 |
Projects at Fyrish 132kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Fyrish Battery Storage | Storage | 200 | Gate 1 | Scoping | 31 Oct 2029 |
| Scotsburn Road | Storage | 170 | Gate 1 | Scoping | 31 Oct 2030 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.