Five Estuaries 220/66 kV Offshore Substation

Five Estuaries 220/66 kV Offshore Substation (NGET) has 1 project in NESO's TEC Register of 23 Oct 2026: 1,080 MW in the queue, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
1
MW in the queue
1,080 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Offshore wind11,080

Projects at Five Estuaries 220/66 kV Offshore Substation

ProjectTechnologyMWGateStatusMW effective from
Five Estuaries Offshore Wind FarmOffshore wind1,080Scoping31 Oct 2030