Grid GuardianOpen this site in the app

Fife Energy Centre 132kV substation

Fife Energy Centre 132kV substation (SPT) has 1 project in NESO's TEC Register of 23 Oct 2026: 100 MW in the queue, 100 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
100 MW
Gate 1 MW
100 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage1100

Projects at Fife Energy Centre 132kV substation

ProjectTechnologyMWGateStatusMW effective from
Fife Energy CentreStorage100Gate 1Scoping31 Oct 2028

Source