FIFE 2 BESS 132KV SUBSTATION

FIFE 2 BESS 132KV SUBSTATION (SPT) has 1 project in NESO's TEC Register of 13 Nov 2026: 49.9 MW in the queue, 49.9 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SPT
Projects
1
MW in the queue
49.9 MW
Gate 1 MW
49.9 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage149.9

Projects at FIFE 2 BESS 132KV SUBSTATION

ProjectTechnologyMWGateStatusMW effective from
Fife 2 BESSStorage49.9Gate 1Scoping14 Jun 2028