Fiddes GSP
Fiddes GSP (SHET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 129.9 MW in the queue, 50 MW Gate 1, and 32.5 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SHET
- Projects
- 5
- MW in the queue
- 129.9 MW
- Gate 1 MW
- 50 MW
- MW connected
- 32.5 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 3 | 129.9 |
| Onshore wind | 2 | 32.5 |
Projects at Fiddes GSP
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Nether Pitforthie BESS | Storage | 50 | Gate 1 | Scoping | 31 Oct 2032 |
| Meetlaw BESS | Storage | 49.9 | Consents Approved | 31 Oct 2031 | |
| Fiddes Battery Storage | Storage | 30 | Scoping | 31 Oct 2028 | |
| Twinshiels (Tullo 2) Wind Farm | Onshore wind | 25 | Built | ||
| Brownieleys | Onshore wind | 7.5 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.