Fetteresso 132kV substation

Fetteresso 132kV substation (SHET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 459.7 MW in the queue, 105 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
5
MW in the queue
459.7 MW
Gate 1 MW
105 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Onshore wind4409.8
Solar3367.8
Storage3312.7

Projects at Fetteresso 132kV substation

ProjectTechnologyMWGateStatusMW effective from
GALILEO 12 LIMITEDStorage, Solar, Onshore wind150.8Scoping31 Oct 2033
Colmealie Wind - Solar - BESS FarmStorage, Solar, Onshore wind112Scoping31 Oct 2037
Fasque WindfarmSolar, Onshore wind105Gate 1Scoping31 Oct 2031
Drumlithie Battery StorageStorage49.9Scoping31 Oct 2028
Craigneil Wind FarmOnshore wind42Scoping31 Oct 2030